| Install
insulation in DRY state. Where cutting is necessary, use a sharp
knife and a straight edge. Butt together firmly. Fit tightly
around all roof protrusions, outlet boxes, vent pipes, etc. Fill
all gaps with off-cuts to avoid heat leakage.
|
|
Metal Decking - Blanket over Purlins
|
- Install building Blankets before
roofing is fixed.
- Lay blankets with factory applied
reflective aluminum foil vapour barrier over and at the right angles
to purlins. (Reflective surface of foil should face downwards).
- Allow sufficient slack for insulation
when laying the reflective foil underneath the blanket to retain its
normal thickness between purlin while still in contact with underside
of decking.
- Where purlin centers are between 700
mm and 1200 mm, lay single sided lightweight reflective aluminum foil
glass fibre single reinforcement, underneath the Blanket.
- Where purlin centers are greater than
1200 mm, use single sided foil cross reinforced glass fibres for
better tensile strength.
- Lap at least 50 mm (2 in.) at joints
and seal with 50 mm (2 in.) wide pressure sensitive aluminum foil tape
.
|