APPLICATION  PROCEDURE

General
Install insulation in DRY state.  Where cutting is necessary, use a sharp knife and a straight edge.  Butt together firmly.  Fit tightly around all roof protrusions, outlet boxes, vent pipes, etc.  Fill all gaps with off-cuts to avoid heat leakage.
Metal Decking - Blanket over Purlins
  • Install building Blankets before roofing is fixed.
  • Lay blankets with factory applied reflective aluminum foil vapour barrier over and at the right angles to purlins.  (Reflective surface of foil should face downwards).
  • Allow sufficient slack for insulation when laying the reflective foil underneath the blanket to retain its normal thickness between purlin while still in contact with underside of decking.
  • Where purlin centers are between 700 mm and 1200 mm, lay single sided lightweight reflective aluminum foil glass fibre single reinforcement, underneath the Blanket.
  • Where purlin centers are greater than 1200 mm, use single sided foil cross reinforced glass fibres for better tensile strength.
  • Lap at least 50 mm (2 in.) at joints and seal with 50 mm (2 in.) wide pressure sensitive aluminum foil tape .
Metal Decking-Blanket under the Purlins
  • Install insulation blanket after roofing is fixed and hydro tested. 
  • Lay blanket with factory applied reflective aluminum foil vapour barrier under at a right angles to purlins (reflective surface of foils should be face downwards).
  • Allow sufficient slack for insulation when fastening under the purlins.
  • Fasten insulation with either steel or aluminum flat bar (25 mm width).
  • Bore hole every .60 m distance and attach with self - tapping screws.
  • Lap 100 mm (4 in.) at joints and seal with 50 mm (2 in.) wide pressure sensitive vapor impervious aluminum foil tape.  
Concrete Slab-Blanket under Concrete Deck
  • Apply adhesive on the concrete slab and plate of mechanical pin (mech. pin spindle should be longer than insulation thickness).
  • Adhere mechanical pin to the concrete slab at 60 mm (24 in.) distance on center in both ways.
  • Impale the insulation blanket on mechanical pin and secure the insulation with pins, attach washers clips.
  • If insulation blanket is faced with reflective aluminum vapour barrier, seal all joints with 75 mm (3 in.) wide aluminum pressure sensitive tape to prevent tranmission of water vapour.back to top

                                HOME    I ABOUT US  I   LOCATION
Acoustic Board Steel Decking Louvers & Lenses  Insulation Downloadable
Ceiling System Fastening Tool Fiber Cements Boards Gypsum Boards Wall & Partitions
   

For questions and comments, send email to:

Copyright © 2002 Petronne  Interior Supply Corporation,  Quezon City,  Philippines